CONCORDIASI - Seychelles test Logistics

Calendar of important events

Seychelles testing

March Cal

To-Do (Completed tasks show up in plain italics)

  • March 2, 2009 - All shippment of HAZMAT must start this date to allow on-time delivery to Mahe (DD batteries)
  • March 12, 2009 -Technical note on the failure analysis due to CNES today
  • March 17, 2009 -  Begin with Medical exams for personnel traveling to McMurdo / Visit of John Rand from RPS (FL1 2124 12PM)
  • April Cal

    To-Do (Completed tasks show up in plain italics)

    • April 1, 2009 - All NON-HAZMAT shipments must be done by this date to allow on-time delivery to Mahe (Seychelles)
    • April 12, 2009 - Begin travel of NCAR personnel to Mahe
    • April 14, 2009 - CNES travel to Mahe
    • April 20, 2009 - The first Tentative flight of MSD and PSC sondes
    • ?? - Tentative return date from the Seychelles of all NCAR personnel

     


    DATES TO KEEP ON MIND

     

    Mc Murdo Operational dates - August 20 -  November 1, 2009  (Tentatively)

    McMurdo Shipping schedule - All equipment MUST be in CHC NLT August 1, 2009 (to be revised!)

     

     

     